Every garden office project is different, but here’s the approximate schedule for a typical installation:

Day 1

Arrive onsite, take delivery of SIP panels and prepare foundations.

Day 2

Lay the floor and erect walls and roof. Install the roofing membrane along with a breathable membrane around the building to keep it water tight.

Day 3

Install all the windows and doors. The first fix electrics can now be fitted along with plasterboard to the ceiling and walls.

Day 1

A plaster skim can now be applied to the ceiling and walls. Externally the cedar cladding can now be installed.

Day 5/6

The external cladding can be finished. Two coats of emulsion can be applied to the new plasterwork along with the second fix electrics.

Day 7

The underfloor heating is installed along with a chosen floor. Once this has been done the skirting can now be fitted.

Day 8

Any touching up with the painting can be done, along with any finishing off anywhere around the building. The customer can inspect and Vivid Green can hand over the keys.